In the early stages of planning the redesign and reconstruction of the Temmler site in Munich, investors were already searching for a waste disposal expert. ELOGplan was commissioned in the middle of 2017 to work on a draft concept for waste disposal and to be included in the planning stages for the three participating architecture firms. Due to the complex and dense building development, the multi-layered use of the site and the diverse range of tenants, the most important task of all was to use the space cleverly to minimise the amount of land used for the recycling centre and to select the most suitable waste disposal logistics plan for the building complex. ELOGplan’s waste disposal plan significantly reduced the originally planned amount of land used and became part of the building application submitted at the end of 2017. “Die Macherei” is an office and commercial quarter with approx. 64,000 square metres gross floor space.